Requirements Elicitation & Validation

Purpose

The purpose of this SOP is to provide Project Managers with a structured, repeatable process for eliciting, analyzing, and validating project requirements. It ensures lean PM teams (1–3 members) can gather accurate requirements from stakeholders, remove ambiguities, and establish a validated baseline that supports planning and scope control.

Poorly defined requirements are the leading cause of project overruns, scope creep, and rework. This SOP prevents those risks by mandating a disciplined approach to requirement gathering and confirmation. It guides PMs through structured elicitation techniques, documentation, and validation checkpoints with stakeholders. The process balances efficiency with rigor, recognizing that Memorres projects often operate with lean resources and fast-moving delivery expectations.

By implementing this SOP, Project Managers create transparency, foster stakeholder alignment, and reduce downstream changes. The defined steps—elicitation, consolidation, validation, and approval—enable requirements to be transformed into a formal specification. The outputs from this SOP directly support baseline creation, schedule development, risk identification, and scope control.

Ultimately, this SOP ensures that requirements management at Memorres is not treated as a one-time activity but as a controlled process that establishes project direction and prevents misalignment throughout the lifecycle.

Scope

This SOP applies to all Memorres projects managed under the Project Management Department. It is mandatory for projects requiring custom software, integrations, or process automation, as well as for strategic internal initiatives. The SOP is applicable whether requirements are captured directly from clients, end-users, or internal sponsors.

The scope covers the structured process of requirements elicitation (interviews, workshops, document reviews, and observation), analysis and consolidation (removing duplicates, prioritizing, resolving conflicts), validation (stakeholder walkthroughs, sign-offs), and ongoing updates during initiation and planning. It also defines roles and responsibilities for PMs, stakeholders, and sponsors.

This SOP does not prescribe engineering practices, detailed functional specifications, or technical solution design, which are the responsibility of delivery teams. Instead, it focuses on capturing business and functional needs at a level sufficient for scope baselining and PM governance.

The responsibility for compliance lies with the assigned Project Manager. Sponsors and stakeholders are responsible for providing accurate inputs and timely validation. The PMO ensures quality checks are met before approving baseline requirements.

Definitions

  • Elicitation: The process of gathering information from stakeholders through structured techniques.
  • Validation: The confirmation that documented requirements meet stakeholder needs and are achievable within constraints.
  • Baseline: The approved version of requirements used as a reference for scope control.

Main Section

Table 1: RACI – Requirements Elicitation & Validation

ActivityProject ManagerStakeholdersSponsorPMOExample
Conduct elicitation sessionsRA/CCIPM facilitates workshops
Consolidate & analyze inputsRCIARemove duplicates
Validate requirementsRACIStakeholders sign draft
Approve baselineCCARSponsor approves, PMO records

Table 2: Workflow – Requirements Elicitation & Validation

StepInputsPM ActivitiesOutputsGate CriteriaExample
1Project Charter, initial assumptionsPlan elicitation sessions, define techniquesElicitation planPlan reviewed by SponsorInterviews scheduled
2Stakeholder inputs, reference docsConduct interviews/workshops, capture raw notesRaw requirements listNotes archived in MICWorkshop notes saved
3Raw requirements listConsolidate, remove duplicates, prioritizeDraft consolidated listAll stakeholders representedDuplicate items removed
4Draft consolidated listCirculate for stakeholder reviewValidated requirementsNo critical conflicts remainSign-off from SMEs
5Validated requirementsPresent to sponsor/PMO for approvalBaseline requirements setSponsor approval recordedCharter linked to baseline

Table 3: Quality Checklist

CriterionTestEvidenceExample
CompletenessAll stakeholder groups consultedAttendance sheet, MIC notesSMEs + Sponsor interviewed
ClarityRequirements are unambiguous and testableRequirement IDs, acceptance criteria“System must allow password reset via email”
AlignmentRequirements align with objectives in CharterCross-reference matrixObjective: onboarding time reduced
ApprovalSponsor approval recordedSigned document in MICSigned baseline v1.0

Closing Note & Cross-References

The Requirements Elicitation & Validation SOP ensures that project needs are captured, consolidated, and formally validated before scope baselines are established. It provides a governance safeguard for lean PM teams, preventing misalignment and uncontrolled scope creep.